A geotechnical report, also called a soil investigation, is an engineer’s assessment of the ground itself: what the soil is, how it is likely to behave, and what footings it can carry. It is not a standard part of a pool removal in NSW. It becomes relevant when something will be built over or near the filled pool, when your approval conditions ask for one, or when the site is sloping or retained. For a fill that will stay as lawn or garden, it is rarely the first thing a certifier asks for, but check your conditions.
When a soil report is likely to be asked for
Something will be built over the fill
AS 2870-2011, Residential slabs and footings, covers site classification and footing design for houses and similar buildings (Standards Australia store). The Housing Industry Association’s summary notes that the standard sets out how a site is classified and that one section deals with filled sites (HIA, Residential slabs and footings). A slab, granny flat, garage or extension over a filled pool therefore usually starts with the designer or certifier asking what the ground is. That question is answered by a geotechnical investigation. The building over a filled-in pool guide covers the rest of that process.
The approval conditions ask for it
The NSW Demolition Code requires a removed pool’s site to be restored to the adjoining ground level with compacted fill (NSW Planning, Demolition of buildings). Any further investigation or testing is set by the conditions of your complying development certificate or development application, so read them before the job is quoted, or ask the certifier.
A partial fill-in
Kiama Council’s fact sheet on the state rule says leaving all or part of the shell in place would need a development application and would likely lead to a title notation identifying buried waste (Kiama Council, Removal of a swimming pool). If anything might later be built over a retained shell, a geotechnical engineer is the person to ask what that means for the ground.
Slopes, retaining walls and drainage
On a sloping block, or where the pool sits against a retaining wall, the questions are how the filled ground will stand and drain. An engineer can assess both. This site has not found a Wingecarribee or Wollondilly rule that makes a soil report compulsory on these sites; it is a professional judgement for the certifier and engineer.
Mine subsidence districts
Bargo, Picton and Wilton are declared Mine Subsidence Districts, and building or extending a structure there needs Subsidence Advisory NSW approval, while demolition itself is on its exempt list (Subsidence Advisory NSW, Mine Subsidence Districts; Exempt Developments List (PDF)). If you plan to build over the old pool there, check with Subsidence Advisory NSW what it will want to see.
What an investigation usually involves
The engineer inspects the site, reviews whatever records exist from the removal (fill dockets, compaction results), and investigates the ground, typically with boreholes or test pits and, where needed, laboratory tests on samples. The report then classifies the site and recommends footing types and any drainage for the proposed structure. The number of holes, their depth and the tests used are the engineer’s call for your site and your building, so ask what is proposed and why.
Soil varies across the Highlands and within a single block. Rather than relying on a general soil map, the engineer reports on your site; the clay soil guide covers why reactive clay matters for a fill.
Before or after the removal?
- Before: if a building over the area is already planned, an engineer can specify the fill, compaction and testing before the pool comes out, so the contractor builds the ground to suit.
- After: the fill can be investigated later, but finding a problem then means digging back into finished ground.
If you are unsure, tell the removal contractor and the certifier what may be built later, and decide before the quote is accepted.
Geotechnical report or engineer’s report?
A geotechnical engineer assesses the soil; a structural engineer designs the footings and structure, often using the geotechnical findings. For a lawn-only fill, neither may be needed. The engineer’s report guide covers when a structural engineer’s sign-off comes in.
Cost
No verified published price exists for a geotechnical report or compaction testing after a pool fill, and this site does not estimate one; the pool removal cost guide lists it as a gap. Ask the engineer for a written fee for your site, and ask the removal contractor to price any testing as a separate line. The pool excavation and backfill page covers what a good backfill quote contains.
Frequently asked questions
If I am not building over the filled pool, do I need a geotechnical report?
Usually not, unless your approval conditions say so. Check the conditions or ask the certifier, and keep the fill and disposal receipts either way.
Is a geotechnical report the same as a structural engineer’s report?
No. The geotechnical report describes the ground; a structural engineer designs what sits on it, often using that report.
What if the investigation finds the fill is not good enough?
The engineer will recommend what to do, which can include further compaction or replacing fill. That is why the fill type, compaction method and any testing are worth writing into the removal contract.
Who should do the investigation?
A geotechnical engineer. Ask for their qualifications, the scope of the investigation and their professional indemnity insurance in writing.
Request a quote and mention any building you plan over the old pool; your enquiry may be passed to an independent licensed contractor who inspects and quotes in their own name.
Sources
- Standards Australia store: AS 2870-2011 (residential slabs and footings), checked 15/11/2026
- Housing Industry Association: Residential slabs and footings (industry summary of AS 2870, site classification and filled sites), checked 15/11/2026
- NSW Planning: Demolition of buildings (pool removal and compacted fill), checked 15/11/2026
- Kiama Council: Removal of a swimming pool fact sheet (PDF) (Kiama’s explanation of the state rule; partial removal and title notation), checked 15/11/2026
- Subsidence Advisory NSW: Mine Subsidence Districts, checked 15/11/2026
- Subsidence Advisory NSW: Exempt Developments List (PDF), checked 15/11/2026