A slope makes pool removal slower and more involved, for four reasons: the machine needs a safe place to stand, broken concrete and spoil want to travel downhill, the new fill has to stay put on the low side, and water running off the slope has to go somewhere once the pool is gone. No published source gives a price premium for sloping sites, so ask for these items to be priced separately in a quote based on a site visit.
Where the machine works from
SafeWork NSW’s excavation code lists local site conditions, including access, ground slope, adjacent buildings and trees, among the things to consider when planning excavation (SafeWork NSW, Code of Practice: Excavation work). Each excavator’s safe working slope is set by its manufacturer, so on a steep block the contractor may cut a level bench for the machine, work from the uphill side and reach down, or use a smaller machine that is slower on concrete. All three add time, which is why a flat-site quote for a sloping block is likely to be wrong.
Spoil, rubble and run-off
The same code says that when excavating in sloping ground, you need to decide which side of the excavation the excavated material goes, considering ground conditions, access, services and the machinery working beside the hole, and that spoil should be kept outside the zone of influence of the excavation (SafeWork code above). On a slope, broken concrete can also roll into fences, walls and gardens below, so ask how rubble will be contained and how often trucks will be loaded.
A CDC for demolition includes erosion and run-off controls as a condition (NSW Planning, Demolition of buildings), and SafeWork’s demolition code says no part of the demolition should cause flooding or water penetration to an adjoining building (SafeWork NSW, Code of Practice: Demolition work). That matters most when the neighbour is downhill.
Holding the fill on the downhill side
Where demolition removes a pool, the Demolition Code requires the site restored to the adjoining ground level with compacted fill (NSW Planning page above). On a slope the low edge of that fill may need support, usually a retaining wall, and the retaining wall guide covers when one needs its own approval. Engineers and certifiers often reference AS 3798-2007 for earthworks; it is a guideline, currently pending revision, not a law (Standards Australia, AS 3798-2007). Your CDC or DA conditions and the engineer set the actual requirement, and the geotechnical report guide explains when a report is worth having. The pool excavation and backfill page covers fill types and compaction.
Wet weather makes this harder. Moss Vale AWS (068239) records a mean annual rainfall of 811.7 mm and a mean 48.8 days a year at or below 2 °C (rainfall from 19 years of records; temperatures 2001-2026) (BOM, Moss Vale AWS). Saturated fill on a slope is harder to compact, so agree standby terms in writing.
Drainage after the pool is gone
A pool on a slope often sits in the path of water running down from higher ground. Once it is filled, the finished surface needs to shed water away from the fill and away from buildings, sometimes with a subsoil drain or a swale. The stormwater management guide covers the options.
What to tell the contractor when you ask for a quote
- a rough idea of the slope, and whether the pool sits at the top or bottom of it
- what is below the pool: lawn, garden, fence, a neighbour’s house
- whether a retaining wall already exists on the low side
- the access path from the street
- photos from several angles, since a slope rarely shows in a single shot
The full pool removal page explains the whole job, and the pool removal cost guide lists published price ranges for a standard removal.
Frequently Asked Questions
What gradient is too steep for normal machinery?
There is no single figure: it depends on the machine, the ground and the manufacturer’s limits. On a very steep block, ask the contractor how and where the machine will stand before you accept a quote.
Do I need a retaining wall after removing a pool on a slope?
It depends on the slope, the soil and what will sit on the fill. Ask an engineer, and check whether the wall needs its own approval.
Is a partial fill-in a cheaper option on a slope?
The published ranges in the cost guide put a fill-in lower than full removal, but Kiama Council’s explanation of the state rule says partial removal would need a DA rather than a CDC (Kiama Council, Removal of a swimming pool fact sheet, PDF). Confirm the approval route with council or a certifier before comparing.
How do I know a contractor can handle a steep site?
Ask them to describe where the machine will work, how spoil and rubble will be contained, and how the fill will be held on the low side. A clear written answer is the best test.
Request a quote: your enquiry may be passed to an independent licensed contractor, who inspects the site and quotes in their own name.
Sources
- SafeWork NSW, Code of Practice: Excavation work (PDF, January 2020): site conditions, spoil placement on sloping ground. Checked 15/11/2026.
- SafeWork NSW, Code of Practice: Demolition work (PDF, August 2019): water penetration to adjoining buildings. Checked 15/11/2026.
- NSW Planning, Demolition of buildings: erosion and run-off controls, compacted fill. Checked 15/11/2026.
- Standards Australia, AS 3798-2007: earthworks guideline status. Checked 15/11/2026.
- BOM, Moss Vale AWS climate statistics: rainfall and frost days. Checked 15/11/2026.
- Kiama Council, Removal of a swimming pool fact sheet (PDF, 2021): partial removal and DA (Kiama’s explanation of the state rule). Checked 15/11/2026.